modeling_of_activities_and_processes [2018/11/01 14:09]
andries [3. Definition of kinds of occurrences, activities, processes and events]
modeling_of_activities_and_processes [2018/11/01 14:27]
andries [4. Specification of activity sequences]
Line 50: Line 50:
 ====== 4. Specification of activity sequences ====== ====== 4. Specification of activity sequences ======
  
-Often it is required to specify in which sequence activities or chains of shall be or are performed. This may result in activity networks. For example, ​in activity scheduling ​for testing, commissioning and start up of facilities ​or to describe ​a maintenance procedure. ​This can be done for sequences of kinds of activities, but also for sequences individual activities, or for procuderes ​in which typical activity sequence is describedthat ​shall be repeated every time that the procedure is followed. \\ +Often it is required to specify in which sequence activities or chains of activities ​shall be or are performed. This may result in activity networks. For example, ​a sequence of activities that specifies a schedule ​for testing, commissioning and start up of a facility ​or the activity sequence that describes ​a maintenance procedure. ​Sequences ​can be specified ​for kinds of activities, but also sequences ​of individual activities, or in procedures ​in which typical ​(individual) ​activity sequence is described that shall be repeated every time that the procedure is followed. \\ 
-For example, ​the following ​activity sequence ​may describe ​steps that shall be taken during a planned maintenance shut-down (also called a turnaround) of facility:+For example, ​a generic ​activity sequence ​that describes ​steps that shall be taken during a planned maintenance shut-down (also called a turnaround) of facility ​may specify a sequence of kinds of activities. For example as follows:
  
-^Name of left hand object^Name of relation ​type^Name of right hand object^+^Name of left hand object^Name ​of kind of relation^Name of right hand object^
 | purge a vessel | shall occurs after a | drain a vessel| | purge a vessel | shall occurs after a | drain a vessel|
 | inspect a vessel | shall occurs after a | purge a vessel| | inspect a vessel | shall occurs after a | purge a vessel|
  
-Whereas ​a sequence of individual activities is expressed as follows:+Typical activities are activities about individual things. Usually they are modeled as individual activities. When used in procedure, the represent imaginary activities, whereas the real activities repeatedly use the procedure as a template. A sequence of typical ​individual activities ​uses other kinds of relations than above. Such a detailed procedure ​is expressed as follows:
  
-^Name of left hand object^Name of relation ​type^Name of right hand object^+^Name of left hand object^Name ​of kind of relation^Name of right hand object^
 | assemble system A | occurs after | clean system A| | assemble system A | occurs after | clean system A|
 | test system A | occurs after | assemble system A | | test system A | occurs after | assemble system A |
 +
 +Further details, for example about specifying partly overlapping activities, are given in the book '​Semantic Information Modeling Methodology'​.
  